Shelter Updates

Here are some updates...

June 2018 - Project Manager hired.

September - Septic Designed approved. Shelter plans finalized.

October 1 - Seeking bids for excavation work.

October 12 - Work started on ground.

October 14 - Ground Breaking Celebration.    

October 25 - Seeking bids for contractor.  

November 2019 - The building construction has started!!

December 2019 - We have walls!!  Roof coming after Christmas.  

February 2019 - We have a roof!

March 2019 - Sliding, Windows and most of the doors are in place!!

Summer 2019 - Outside ground work, water, septic and plumbing...

October 2019 - Inside walls are in.  Electrical work starting.... 

March 2020 - Road is been developed.  Electrical work is almost finished.  Heating and ventilation systems are being installed.  Shed has been built.  Drywall starting now....